Ordering a steel frame: from the parts list through delivery to installation

In brief

A lorry carrying steel structure components may arrive on schedule and installation may still not begin. The reason is sometimes an unfinished foundation, no space for unloading or a discrepancy in the documentation. Purchasing a steel hall with delivery is therefore best considered as a sequence of linked actions. The list of profiles matters, but the conditions under which they are received and installed are equally important. The frame of a steel hall consists of main and secondary components and connections. The schedule must distinguish between frames, purlins, wall rails, bracing and opening frames. Bolts, anchors and other accessories must be checked separately. The absence of a small component can halt work on a larger part of the structure.

Steel building under construction with an open front and bundles of sections on site

Determine what the delivery covers

For modular steel structures, the markings should correspond to the installation drawings. A repetitive appearance of the profiles does not mean they can be swapped around. They may differ in length, thickness, holes or function. Acceptance by component numbers is more reliable than assessing completeness on the basis of the number of packages.

The documentation must have a single version

Before dispatch, the approved geometry of the steel hall and the arrangement of openings must be agreed. Changing a gate after the components have been manufactured may affect the wall rails, auxiliary columns and cladding. It is therefore important to specify the current version of the drawings. The same set should be the basis for production, foundations and installation.

Steel structures require information on connections, supports and the sequence of work. The documents should also specify the assumptions for installation safety measures. They should not be replaced by photographs of a similar building. Two halls of similar form may have a different bracing arrangement and a different detail for the connection to the foundation.

Check the foundation before arrival

The position of the steel hall must correspond to the design. The axes, levels and position of the anchors are important. An incorrectly set anchor can prevent installation of the base plate. Completion of concreting alone does not mean readiness for loading. The requirements of the design, the condition of the concrete and confirmation of the works carried out must be taken into account.

The scope of the check should be agreed between the foundation contractor and the steel structure erector. Identifying discrepancies before transport allows time to design a solution. Drilling holes or bending components on site without agreement is not the proper way to adapt the set to an error in the substrate.

Plan access and unloading

Long components require checking the access route, turning radii and stopping place. The capabilities of the unloading equipment and the condition of the ground beneath its supports must be established. A steel hall may stand on a large plot and yet access to the installation point may prove tight. Overhead lines, existing structures and access restrictions also matter.

Before purchase, it must be determined whether transport includes unloading, who provides the equipment and who directs the work on site. The rules for accepting successive batches should also be agreed. Delivery of the entire set at once does not always make installation easier. On a small site, a sequence linked to the progress of the works may be more advantageous, if the supplier provides for it.

Steel-framed buildings – free quote from SteelProfil
Steel-framed buildings – free quote from SteelProfil

Storage affects the condition of the components

The steel structure should be stored on prepared ground in accordance with the supplier’s recommendations. Water accumulation and contact between components and the ground must be limited. Packages must not block working routes or access to the parts needed first. Protection of the coatings during handling is also important.

During acceptance, the markings, the number of parts and visible damage are checked. Irregularities should be recorded before unpacking further batches. This also applies to the components of the steel hall cladding. Sandwich panels have their own transport and installation requirements. They should not be treated as arbitrary sheets of metal.

Installation needs agreed boundaries

The order should clarify who carries out repairs to damaged coatings, inspection of connections and work on flashings. A steel hall is ready for the next stage only after the agreed scope has been completed. The absence of clear boundaries of responsibility encourages disputes, especially when the cladding and services are installed by different teams.

Before delivery of the steel hall, designate a place for vehicles and an area without access for unauthorised persons. Leave time in the schedule for checking completeness and conformity of markings. Document differences between the delivery and the approved schedule of components. Steel structures are installed according to the design, even when the set looks simple. Do not carry over to the site decisions that may change the load-bearing capacity of a connection.

Confirm that equipment access remains possible even after the weather deteriorates. Check whether the markings will remain legible after the packages have been spread out on site. Comparison of offers should cover the entire delivery service, not only transport. Match the transport sequence to the approved installation organisation. A well-prepared acceptance reduces downtime caused by simple organisational shortcomings. Keep the acceptance confirmations.

Check access to the power supply.

7 branches. Materials closer to your project.

Map of seven branches offering sandwich panels, PIR boards and sheet metal — Ecoprofil
  • SEROCK — Dzierżenin 34 E [map]
  • BŁONIE — ul. Sochaczewska 138A [map]
  • RADOM — ul. Grobickiego 8 [map]
  • ŁÓDŹ — Natolin 8 [map]
  • OLSZTYN — Barczewo, ul. Prosta 9 [map]
  • WROCŁAW — ul. Jerzmanowska 10C [map]
  • GORZÓW WLKP. — ul. Zielona 33/34 [map]

Check prices and availability: +48 500 409 109

Free quote

Materials for your project

You may also find useful…