What should a quotation for a complete sandwich panel roof include?

At a glance

A sandwich panel roof budget should cover everything needed to make the roof weathertight and drain rainwater. Check whether the quotation includes gutters, service penetrations, lifting equipment and preparation of the supporting structure. When replacing an old covering, allow for removal and for protecting the space below. Agree the scope before comparing prices per square metre. Measure the length along each slope, its width, the eaves projections and any changes of pitch. Use the effective cover width to list how many panels you need at each length. A single area figure makes cutting waste difficult to estimate.

Light-coloured sandwich panel roof with drainage along the eaves

Measuring the sloping roof area

Rooflights, chimneys and vents each reduce the area of panel at an opening, but each also needs support, cutting, edge finishing and sealing. A small roof with many penetrations can cost more per square metre than a large uninterrupted slope. Check the drawings for joints between panel ends and include the accessories these joints require.

Specifying the roof panels and supports

Specify the core material, panel thickness, facings and coating to suit the required roof performance. Check support spacing, bearing widths, loads and the pitch permitted for the system. A minimum pitch quoted for one panel arrangement without rooflights or end laps applies only under the stated conditions.

If rooftop equipment or photovoltaic modules are planned for later, include their loads and fixings in the structural design. Check the capacity of any proposed attachment to the ribs of the outer facing. On an existing building, have the purlins and their connections assessed. The capacity of the existing frame still needs checking when the roof covering is replaced.

Pricing the full scope of work

This example assumes an order for 240 m² of panels for a simple roof. All prices are illustrative and exclude VAT. Unit rates are rounded for display. The line totals use the unrounded rates.

Example itemCalculationCost excluding VAT
Roof panels240 m² at approximately €34.72 per m²€8,332.20
Flashings, fixings and sealsLump sum allowance€1,434.99
Installation of roof panels240 m² at approximately €11.11 per m²€2,666.30
Transport and equipmentLump sum allowance€879.51

The listed items total €13,313.00 excluding VAT, or about €55.47 per square metre of panels purchased. For an actual building, the quotation must also say whether gutters, penetrations and structural work are included. The example total covers only the items shown.

Keeping the building in use during reroofing

Removing an old roof requires a plan for waste and for protecting the building below. If the premises remain in use, agree the work sequence, how machinery will be protected and which areas will remain accessible. Taking off an entire slope in one operation may be impractical. The amount of roof that can be safely closed up at the end of each day may determine the pace more than the panel installation rate.

Before accepting a quotation, agree who will inspect the structure once it is exposed and how necessary repairs will be priced. List removal of old components and reinstatement of services separately. Identify materials that require special handling in advance. Record uncertainties about the existing building so that you can see which costs are still open.

First-quality PIR insulated roof panels – free quote from SteelProfil

Checking site access and equipment hire

Panel length affects the delivery vehicle, lifting method and space needed alongside the building. Check that the equipment can reach the most difficult part of the roof from an available set-up position. Hire costs depend on the time booked and when that position is accessible. A late delivery can leave hired equipment standing idle before installation begins.

Compare what each contractor allows for work at height, access platforms, panel lifting attachments and on-site handling. A labour-only rate per square metre leaves equipment to be priced separately. Agree how weather delays will be handled and charged. These details show whether the quoted price covers the way the job will actually be done.

Planning for the first season and subsequent maintenance

Allow for inspections of drainage, fixings, coatings and service penetrations. Plan safe access while the layout can still be changed. A hard-to-reach gutter or a unit installed over a critical joint can increase the cost of every maintenance visit.

Assess energy savings from a thicker panel in the context of the whole building envelope and its heating system. Retain the insulation performance the building requires when comparing discounts. Each quotation should describe a complete roof that can be maintained, identify the documents to be handed over and the items to be checked at acceptance, and state what is priced separately.

Frequently asked questions

Does the installation price include stripping the old roof?

Only if the quotation expressly includes it. Check waste removal, protection of the interior and any repairs needed once the supporting structure is exposed.

Will a single long panel always make the roof cheaper?

A long panel can reduce the number of end joints, but may cost more to deliver and lift. Compare complete layouts that meet the design requirements, including the equipment and access each one needs.

7 branches. Materials closer to your project.

Map of seven branches offering sandwich panels, PIR boards and sheet metal — Ecoprofil
  • SEROCK — Dzierżenin 34 E [map]
  • BŁONIE — ul. Sochaczewska 138A [map]
  • RADOM — ul. Grobickiego 8 [map]
  • ŁÓDŹ — Natolin 8 [map]
  • OLSZTYN — Barczewo, ul. Prosta 9 [map]
  • WROCŁAW — ul. Jerzmanowska 10C [map]
  • GORZÓW WLKP. — ul. Zielona 33/34 [map]

Check prices and availability: +48 500 409 109

Free quote

Materials for your project

You may also find useful…